Revision works on the depot Svenska Väg AB Diverse metal and installation tasks on road construction machinery. Installation of machines, lathe work, welding methods used: MMA, MIG
Skärblacka Recovery ORAB Entreprenad AB Welding work on several materials and dimensions, mainly with TIG and MMA, pipe installation with isometric and axonometric drawings.
Fortum Värme Akallaverken Rörentreprenad Björnbergs Industri AB Installation of DN80 stainless steel pipeline, heat exchanger, pumps, concrete pouring for pump foundation, installation and brazing of copper lines. Installation of several door frames and doors as well as a 9 m spiral staircase and 3 door platforms. Pipe installation with isometric and axonometric drawings.
Fortum Värme Hammarbyverket Björnbergs Industri AB TIG welding on DN50 pipeline, installation of valves and manometers
2012
An Albatross project on Eldfisk, Bergen Adukta AS Norway Overhaul on oil rig Eldfisk onshore at Bergen. Welding processes used: MMA and TIG welding
KVV6 Stockholm, Björnbergs Industri AB Björnbergs Industri AB Industrial piping installation and welding according to PED, overhaul
Fortum Värme AB Hammarby Björnbergs Industri AB TIG welding on black and stainless steel pipe
KVV6 Stockholm, Fortum Värme AB A Viirre Projektsvets AB Mirror welding with TIG on stainless steelpipe
Vetlanda ORAB i Öst AB TIG welding on black and stainless steel pipe
Fortum Brista 2 Björnbergs Industri AB TIG welding on stainless steel pipe, fitting HPAC pipe from the roof
Skärblacka Recovery 2012 ORAB i Stockholm AB Welding work on several materials and dimension, mainly with TIG and MMA
Fortum Värme Akallaverken Stålentreprenad Björnbergs Industri AB Erection of a new building for switchgear (150 mm Lindab sandwich panels), fitting and welding work on 15 000 KG steel constructions containing beams, pillars, and reinforcement plates on existing construction. Modification of existing pillar foundations by chipping and pouring of extra concrete. Construction of a frame support for a coolant system on the roof top.
2011
L&T Recoil Oil Refinery Fredrikshamn, Finland YIT Industry Services Oy Overhaul of entire oil refinery pipe system, methods 141, 111 stainless steel and oil pipes
Hallstavik Pappersbruk, Sweden ORAB i Gävle AB 2 mm stainless steel pipe welded with: 111! X-ray control 10-100%!, fitting works
Stockholms Arenan PEAB Welding on heavy construction steel up to 60 mm, 135/136
Coolant system Gothenburg Svensk Licenssvetsning AB TIG welding on coolant systems pipelines in a warehouse.
KVV6 Värtan, Stockholm Björnbergs Industri AB Industrial piping installation and welding according to PED, used welding process: MMA
Pappersbruk, Valvik ORAB i Gävle AB 2 mm stainless steel pipe welded with: 111! X-ray control 10-100%!, pipe installation with isometric and axonometric drawings.
2010
District heating pipelines, Helsinki, Finland Finorest Oy Pipe lines for district heating, large diameters, welding processes: 311 (rightward welding), 111
KVV6 Värtan, Stockholm Fortum Värme AB RFX Industri AB MMA Industrial piping installation and welding according to PED, maintenance
Fortum Värme AB Hornsberg Thermal Energy Storage, Stockholm RFX Industri AB Installation of pipelines and other pressurized equipment for district cooling. Used methods TIG, MMA
Energi och Miljö AB Borås Ryaverket Eksjö Svetsmontage AB Welding work on constructions. Used methods: MIG MAG
2008-2009
Söderenergi AB Igelsta CHPDH power plant, Södertälje, Boiler room Foster Wheeler Energia OY Pipe welding PED 97/23 EU, 141, 111 stainless steel, black steel Fitting with acsonometric and isometric drawings.
Igelsta CHPDH -power plant Turbine hall Siemens AG Pipe welding PED 97/23 EC, construction welding on turbine foundations, 141, 111
KVV6 Värtan, Stockholm Fortum Värme AB RFX Sverige AB Industrial piping installation and welding according to PED, maintenance and revision